Reading Commons Specific Involvement: furniture and finishes coordination; power/data coordination at systems furniture
Above: Mid-way through the design process for the Children's Library, the concept for the main feature was unresolved and lacking clear direction as to how to proceed. On my own initiative, I pitched the concept of "Little Library, Big City" to BPL Leadership. The concept drew upon other Boston-specific themes that were coalescing in other parts of the room at the time. The idea was well-received and the concept was approved as a directive for the design team where it was further developed into what eventually became "StoryScape".
View PDF
StoryScape Specific Involvement: pitching original concept to BPL Leadership; preparation of RFP scope and vendor evaluation; guidance throughout design development; technical coordination with fabricator; collaborative working relationship with fabricator including preparation of design details; punch list
StoryScape Reading Stoop
StoryScape Example: detail drawing of stoop for coordination with fabricator
View PDF
Pathway to Reading | Sensory Wall Specific Involvement: preparation of design drawings; component selection and curation; bid document preparation and vendor evaluation; installation coordination; budget tracking including review of payment requisitions
View PDF
Pathway to Reading | Sensory Wall Specific Involvement: preparation of design drawings; component selection and curation; bid document preparation and vendor evaluation; installation coordination; budget tracking including review of payment requisitions
View PDF
Pathway to Reading | Sensory Wall Completed installation
BookBirds Specific Involvement: preparation of design drawings; RFP scope and vendor evaluation; guidance throughout design development; technical coordination with fabricator; collaborative working relationship with fabricator; installation coordination; punch list
Detailed view of BookBirds
Book-Bird Sculpture Example: technical drawings for RFP scope of work
View PDF
Book-Bird Sculpture Example: technical drawings for RFP scope of work
View PDF
Example: finish schedule for Book-Bird RFP scope of work
View PDF
Interactive Lion Cub Sculptures Specific Involvement: vendor selection; guidance of fabricator throughout design development; shop drawing review; collaborative detail development; site visit during fabrication; scheduling; installation coordination; budget tracking and review of payment requisitions
Teen Central Decor Coordination Example: excerpted presentation slide of internal pitch to Leadership regarding proposed items for display
View PDF
Teen Central Decor Coordination Example: excerpted presentation slide of internal pitch to Leadership regarding proposed items for display
View PDF
Teen Central Decor Completed Installation
Teen Central Decor Completed Installation
Teen Central Decor Completed Installation
Teen Central Decor Completed Installation of disassembled card catalog display
Teen Central Decor Completed Installation of disassembled card catalog display
gLike
Boston Public Library | Central Library Renovation, phase 1

completed: 2015
size: 150,000 gsf
cost: $16.1m
role: BPL Major Projects Co-Manager
phases of involvement: SD, DD, CD, CA, close-out, occupancy
architect: William Rawn Associates
contractor: Consigli
delivery method: CM-at risk

View Website
Available
Sydney Thiel
Project Manager, University of Washington Seattle, WA